Overview of upcoming work as of June 18, 2019

Starting as early as Wednesday, June 19, the contractor will return to the corridor to complete remaining items on the final project checklist. Work may include the following activities: 
  • Electrical work for pedestrian signals
  • Landscape restoration in some planting strips 
  • Drainage and manhole maintenance 
  • Curb ramp replacements or retrofitting
  • Additional concrete work on curbs and sidewalks, as needed
For those of you that have been following construction for this project since the beginning, you may wonder why we are replacing curb ramps that were recently installed. While many of the new curb ramps appear accessible, some of them do not meet the strict American with Disabilities Act (ADA) regulations and requirements. These design standards are an important part of this project and ensure that all people have the proper accommodation to travel throughout the city.

What to expect during remaining work

The remaining work will primarily take place throughout the corridor on sidewalks, curb ramps and planting strips. During work, people traveling on 35th Ave NE between NE 45th Pl and NE 89th St can expect: 
  • Typical work hours: Monday – Saturday 7 AM to 7 PM
  • Detours for people walking: For your safety, please follow detour signs near work zones
  • Traffic lane shifts: 1 lane of traffic in both directions will be open at all times. 
    • Uniformed police officers (UPOs) and flaggers will direct traffic around the work areas, as needed
    • Turns may be limited to and from intersections while crews work on curb ramps
  • Parking restrictions: On-street parking will be restricted near active work areas to provide a safe space for crews to work
Stay informed
You can find more background about this project on our webpage. Please forward this email to those you think will be interested or share this link to sign up to receive construction updates by email. If you have questions, please contact us at 35thAvePaving@seattle.gov or 206-512-3950.
Contact
35th Ave NE Project Outreach Team
Seattle Department of Transportation
Construction information line: (206) 512-3950
35thAvePaving@seattle.gov
www.seattle.gov/transportation/35thNEpaving.htm
For translation services, please call (206) 512-3950.
Servicios de traducción e interpretación disponibles bajo petición (206) 512-3950.
Matutulungan ka naming maintindihan kung hihingi kang tulong (206) 512-3950.
요청하시면 번역이나 통역을 제공해드립니다 (206) 512-3950.
Dịch và thông dịch viên sẵn sàng nếu có sự yêu cầu (206) 512-3950.
Haddii aad dooneyso turjubeen fadlen wac (206) 512-3950.
Tajaajiliwwan hiikkaa fi turjumaanaa yoo karaa (206) 512-3950 tiin gaafattan jira. 
በ (206) 512-3950 ጥያቄ በማቅረብ የትርጉም እና አስተርጓሚ አገልግሎቶች ይቀርባሉ፡፡
ብዝቐርብ ሕቶ መሰረት ግልጋሎት ትርጉም ኣሎ እዩ (206) 512-3950::
Copyright © 2019 | Seattle Department of Transportation | All rights reserved.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
SDOT · 700 5th Ave · Seattle, WA 98104-5058 · USA

Email Marketing Powered by Mailchimp