Next week crews plan to complete installing topsoil and hydroseeding in planting strips. Crews will also do concrete work on sidewalks as needed throughout S Columbian Way and S Alaska St.

This week, crews removed striping on S Columbian Way west of Beacon Ave S to prepare the road for new striping and protected bike lanes.

Crews will begin to paint final striping on the road beginning as soon as Monday, June 24.

Please DO NOT drive on fresh paint. If the paint is disturbed, crews will need to come out again and redo those lines.

Please see below for additional details about upcoming work.

Upcoming work
Map of project including extent of protected bike lanes
What to expect during final striping
  • Work hours: As early as Monday, June 24, 7 PM to 7 AM
  • Striping will take up to 2 weeks to complete
  • Noise from striping will be slightly louder than regular traffic noise
  • Expect strong odors and large equipment
  • Emergency vehicles will still be able to access the street
Driveway access will be restricted for at least an hour while the striping paint cures. If you anticipate needing to use your vehicle, please plan to park on side streets.

Please DO NOT drive on fresh paint. If the paint is disturbed, crews will need to come out again and redo those lines.

Next week
  • Crews will begin to install top posts to mark the protected bike lanes
What to expect during construction
Qué esperar (haga clic aquí) | Những gì sẽ xảy ra (bấm vào đây) | 想了解有關信息 (點擊此處) | 예상할 것 (이곳을 누르세요) | Ano ang maasahan (i-click dito) | Maxaad fileysaa (riix halkan)
  • On-street parking and lane restrictions near work locations
  • Temporary sidewalk and crosswalk closures with signed detours
  • Noise, dust, concrete odors, and vibration
  • Access to businesses and homes will remain open
  • Work is weather dependent, so timing of work may change if needed
  • Bus stops in the work zone will be closed during work hours. For more detailed information, check out King County Metro's Rider Alert website.
For more information and translation, please call 206-256-5112. | Para mayores informes y traducción del material, por favor llame al 206-256-5112. | Để biết thêm thông tin và dịch thuật, vui lòng gọi 206-256-5112. | 需要更多的信息及翻譯資料,請致電 206-256-5112. | 추가 정보와 변역을 원하시면, 206-256-5112 에 전화하세요. | Para sa karagdagang impormasyon at pagsasalin, mangyaring tumawag sa 206-256-5112. | Warbixinno dhaaraad ah fadlan soo wac 206-256-5112.

Stay connected
  • Contact us directly at ColumbianAlaska@seattle.gov or leave a voicemail at (206) 256-5112
  • Visit our project website to learn more about the project
  • Request a briefing for your business or organization via email or phone
Please forward this email to others you think may be interested, or go to the project website to sign up for construction email updates.

Thanks for your patience and support while we complete this project. We’re working to minimize construction impacts as much as possible.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
EnviroIssues · 101 Stewart St Ste 1200 · Seattle, WA 98101-2449 · USA

Email Marketing Powered by Mailchimp